Report Tools
Explanation
This activity is used to report the Tool time used in executing the work
assignment. It only allows to report against the tool groups that has been
connected to work task.
Prerequisites
- B2B interface, Execute Work must be available and
accessible.
- Log in user must have the respective B2B Supplier - User connection.
- There must be an assignment created against the logged in user.
- Assignment status must not be either completed, in completed or pending
completion.
System Effects
As a result of this activity, Time transaction are created against the respective work task.
Related Window Descriptions
N/A
Procedure
Use the following procedure to report the Tool time spent on a work assignment.
Report in Work Assistant,
- Open the Subcontract Work Orders > Execute Work
Lobby Page.
- Find the Lobby section for Ongoing Assignments and click on it
to list started work assignments.
- Select one Work Started assignment.
- Click on the Complete command button. It results into open the Report In
Work assistant.
- Open Report Tools sub group.
- Select the used tool and enter the number of used hours.
- Add a comment if required.
- Finish the assistant.
Work Task Details page,
- Open the Subcontract Work Orders > Execute Work
Lobby Page.
- Find the Lobby section for Ongoing Assignments and click on it
to list started work assignments.
- Select one Work Started assignment.
- Choose Work Task Details button to navigate into respective work
tasks.
- Open the Report tab and Tool Report sub group.
- Select the used tool and enter the number of used hours
- Add a comment if required.
- Save the changes.