Readjust Visits
Explanation
Use this activity to adjust the visit chain according to the changes in
remaining time to complete an activity or any deviation of activity duration
and total allocated hours.
This activity is typically used when:
- Work task is set as Allow Multiple Visits selected and,
- There is a deviation between resource activity duration and total
allocated hours.
Prerequisites
- Visit chain must exist.
- Readjustment needed symbol should be visible in the visit chain/work
assignments.
System Effects
Work Assignments are updated as below
- If date period and allocated hours of the existing visit is updated,
corresponding work assignment is updated accordingly
- If new visits are created, work assignments with status Assigned are
created.
- If visits are removed, work assignments with status Assigned and
not set to mobile will be deleted and work assignment with status above
Assigned or set to mobile will be Canceled
Window
Resource
Monitoring Gantt
Related Window Descriptions
Resource Monitoring Gantt
Procedure
Readjust Visits
Follow this procedure to readjust visits:
- Populate the Resource Monitoring Gantt in a way so that the
visit chain that
should be readjust.
- Select the work assignment/visit with Readjustment Needed
symbol and select the right mouse option Readjust.