Define Scheduling Dependency Attributes for Work Task

Explanation

This activity is used to define scheduling dependency attributes between dependent work tasks within a work order. These attributes will  govern the scheduling behavior of pre-requisite activities in Planning and Scheduling Optimization when scheduling work tasks.

Prerequisites

Before defining scheduling dependency attributes, the following must have been completed:

System Effects

As a result of this activity, scheduling dependency attributes between dependent work tasks will be defined. The dependency attributes are used to control the scheduling behavior in PSO scheduling for the work tasks.

Window

Work Task
Work Tasks
Prepare Work Order
Work Order Structure

Related Window Descriptions

Work Task
Prepare Work Order
Work Order Structure

Procedure

Use the following procedure to enter the information:

  1. Navigate to the Service and Maintenance/Work Management/Preparation and Planning/Work Task or the Work Tasks window, alternatively select the Work Task tab in the Service and Maintenance/Work Management/Preparation and Planning/Prepare Work Order or the Work Order Structure window.
  2. Right-click and click Dependencies to open the Dependencies dialog box.
  3. In the dialog box, select the work task(s) that should be defined as predecessor work task(s) by selecting the Set Dependency check box.
  4. Click Save and Close to save the information and close the dialog box.
  5. Right-click on the work list line and select Scheduling Dependency Attributes to open the dialog box.
  6. In the dialog box, the dependent work task(s) will be listed.
  7. The work tasks that are dependent to the selected work list line will be shown in the list. Select if to change the attribute values for the dependency. It is possible to change any of the following attributes All or Nothing, Same Resource, Min. Delay (Minutes), Max. Delay (Minutes), Overlap allowed.
  8. Click OK.