Complete Work Assignment
Explanation
This activity is used to complete the work assignment by the assignee, once
the execution is done. It can be performed on assignments in work started status
or pending completion status. Completion of an assignment guides the assignee to
report time and tools on the assignments, in addition to issue and return
materials.
Prerequisites
- B2B interface, Execute Work must be available and
accessible.
- Log in user must have the respective B2B Supplier - User connection.
- There must be an assignment created against the logged in user.
- Assignment Status must be Work Started or Pending Completion.
System Effects
As a result of this activity, work assignment is set as completed.
Related Window Descriptions
N/A
Procedure
Use the following procedure to complete a started work assignment.
Assignments List pages,
- Open the Subcontract Work Orders > Execute Work
Lobby Page.
- Find the Lobby section for Assignments.
- Click on the Ongoing or All Assignments counters to list all
accepted work assignments.
- Select one or more Work Started assignments and click on Complete
command button at
the top of the lines. It results into open the Report In
Work assistant.
- Report Time and Tools. Issue & Return materials.
- Finish the assistant.
Work Task Details page,
- Open the Subcontract Work Orders > Execute Work
Lobby Page.
- Find the Lobby section for Assignments.
- Click on the Ongoing or All Assignments counters to list all
accepted work assignments.
- Select one or more Work Started assignments and choose Work Task
Details button.
- Click on Complete command button at
the top of the page. It results into open the Report In
Work assistant.