Use this activity to promote work assignment status from Resource Monitoring Gantt.
In addition to the general prerequisites, listed in Maintenance Resource Setup:
Work assignments must exist for the resources that are monitored.
Work Assignment status is updated.
Resource Monitoring Gantt
Resource Monitoring Search
Legend
The Planner/dispatcher/service manager/ call center user also sometimes has to manage and/or control the execution of work assignments at the same time as monitoring resources. For this purpose it is also possible for the user to promote work assignments in Resource Monitoring Gantt.
Follow this procedure to change the status of a work assignment in Resource Monitoring Gantt:
For more details read about: