Schedule Operation Block

[About Operation Block] [About Shop Order Infinite Scheduling]

[To Shop Order Planning]

Usage

Use this dialog box to schedule shop order operations connected to an operation block in sequence, or in parallel. The operation block can be scheduled either forward from a given start date, or backward from a given finish date.

Note: New start/finish date will be based on the infinite scheduling logic and may differ from the value seen in the dialog box. For instance, if the provided new start date is on a non working date, the operation will receive a new start date corresponding to the first available work date/time from the value given.

Activity Diagrams

Create and handle operation block

Activities

Forward schedule block operations in parallel
Forward schedule block operations in sequence
Backward schedule block operations in parallel
Backward schedule block operations in sequence