Enter Other Demands
Explanation
This activity is used enter external, expense and fixed price lines to the work
task..
Prerequisites
- The service quotation must be in the Under Preparation status.
- A work order and a work task should be created or
connected with all the necessary information within the service quotation.
- If other demand is to be connected to a work task template, the
work task
templates must have been
defined on the Jobs and Templates tab on the work order prior
to connecting the other demands to the work task.
- Non-inventory sales parts should be created in IFS/Sales and
procurement.
System Effects
As a result of this activity, a work task is planned with
external, expense and fixed price lines..
Window
Service
Quotation
Related Window Descriptions
Service Quotation
Service Quotation/Work Orders and Tasks
Service Quotation/Work Orders and Tasks/Work
Task/Other Demands
Procedure
- Open the Service Quotation window and query for the
required quotation (F3).
- On Work Orders and Tasks tab, expand the tree navigator on
the left pane and click on a work task. Work Task tab is
populated with the information of the selected work task..
- Select the Other Demands tab and add a new record (F5).
- Select a Cost Type and enter values for Cost, Sales
Part and Planned Quantity. Use List of Values to select a sales
part.
- Save the information (F12) and repeat steps 3 and 4 as required.