Set Up Basic Data to Enable Overhead to Project Labor Time

Explanation

In order to have an overhead cost added to the project time transaction postings, you need to set-up the following:

  1. Posting control for posting types PRJT1, PRJT2, PRJT3, and PRJT4 must have been defined.
  2. Cost details must have been entered in the Cost Details Basic Data window in IFS/General Data for Inventory and Distribution.

In the Cost Details Basic Datawindow you need to do the following:

  1. Select the preferred cost source indicator.
  2. Enter the cost source ID's that should be used, and their overhead rate.
  3. Connect the cost source ID to the corresponding cost source indicator.

 

Window

Cost Details Basic Data

Related Window Descriptions

Cost Details Basic Data

Procedure

N/A.