Report Progress for Resource Assignment
Explanation
Perform this activity to report progress for a resource assignment on an activity.
There are two ways of obtaining progress for a resource: manually; or
through project reporting, i.e., when the employee connected to the
resource group reports his or her time on the activity.
Prerequisites
- A project activity must exist.
- The Resource Group must have been defined with the project's connected company.
- The employee must be connected to the resource group.
- A Valid Report Code must have been defined for the activity.
System Effects
- Earned value for the Resource Group is calculated by the system according
to the progress entered. The value is estimated by using the formula:
Progress * Revised Hours (or Planned Hours)
- Progress is calculated based on the hours reported on the activity.
Window
Activity Resources
Resource Group/
Activities
Project
Navigator/Resource
Activity/Resource
Related Window Descriptions
Activity Resources
Resource
Group/Activities
Project
Navigator/Resource
Activity/Resource
Procedure
Report progress manually:
- Select the activity where progress will be updated.
- Enter the progress value in percentage.
- Save.
To obtain progress through project reporting, follow the steps described in
activity Register
Project Time (under Human Resources/Report Project Time and Cost), then
follow up the progress calculated for the selected activity.