Connect Cost/Revenue Breakdown Structure to Project
Explanation
The cost/revenue breakdown structures that belong to a company can be connected to
projects in the same company. Once connected a structure can be used to plan
project budgeting and forecasting.
Prerequisites
- A cost/revenue breakdown structure that is in the Active state
should exist.
- A project that belongs to the same company as the structure should exist.
System Effects
- The structure will be connected to the project and is to be used for
planning in project budgeting and forecasting.
Window
Project
Related Window Descriptions
Project
Procedure
- Open the Project window and query for your
project.
- Enter the relevant structure ID in the CBS ID field. The List of
Values will show the structures available for the company.
- Click Save.