Connect Existing Object to Activity
Explanation
Perform this activity to connect existing objects to a project activity, such
as a Material Requisition line, Purchase Requisition
Part line, Purchase Requisition No Part Line, Purchase Order
Part line, Purchase Order No Part Line, Customer Order line, Shop Order, DOP
Header or a Design object.
Prerequisites
- The
project to connect to must be in status Approved or Started.
- The project must be approved to be able to connect the following objects: Customer Order Line, Material Requisition
Line, Purchase Order Part Line, Purchase Order No Part Line and Shop
Order. Objects such as Change Order, Document Package, DOP Header, Design
Object, Purchase Requisition Part Line, Purchase Requisition No Part Line
and Tasks can be connected when the status of the
activity is Planned or Released.
- The site
of the object must be defined as an allowed site for project it is
connecting to.
- To connect
a Material Requisition Line,
- The material requisition line must have the Planned or Released status.
- The material requisition line must not be connected to a project
activity.
- The material requisition line must not have the Purchase Order supply
code.
- Posting control rule M53 should be defined.
- To connect a
Purchase Requisition Line,
- The purchase requisition line must not have PO Created status.
- The purchase requisition line must not be connected to a project
activity.
- The purchase requisition line must have demand code Inventory Order or
Non Inventory (for non-inventory parts and no-parts)
- The purchase requisition line shall not have any exchange components.
- The posting control rule M1 should be defined when purchasing
inventory parts and posting control rule M93 when purchasing non-inventory
purchase parts and no-parts.
- To connect a
Purchase Order Line,
- The purchase order line must have the Released, Stopped or Confirmed
status.
- The purchase order line must have demand code Inventory Order or Non
Inventory (for non-inventory parts and no-parts).
- The purchase order line must not be connected to a project activity.
- The purchase order line must not be manually pegged to a customer order
line or a shop order material line.
- The purchase order line shall not have any exchange components.
- The posting control rule M1 should be defined when purchasing
inventory parts and posting control rule M93 when purchasing non-inventory
purchase parts and no-parts.
- To connect a
Customer Order Line,
- The customer order line must have the Released status.
- The customer order line must have the Invent Order, Pkg, Non
Inventory, Purch Order Trans, Int Purch Tran, Purch Order Direct, Int
Purch Direct, Shop Order, Dop Order or Not Decided supply code.
- The customer order line must not be connected to a project activity.
- The customer order line must not be manually pegged to a purchase order
line or a shop order.
- The customer order line must not be a customer consignment stock
delivery.
- If the customer order head is connected to a project it is not allowed
to connect any customer order line to another project.
- The posting control rule M24 should be defined when procuring
inventory parts and the posting control rule M26 when procuring non-inventory
parts through customer order line.
- To connect a
Shop Order,
- Only Shop Orders in the Planned status can be connected to an activity.
- The shop order can not be connected to several activities - it's only
possible to connect a shop order to one activity.
- The shop order must have demand code Inventory Order, in other words
only ordinary shop orders and repair shop orders can be connected. Any MRO-related shop orders like assembly, disassembly or disposition shop
orders can not be connected manually to the activity.
- Posting control rule M40 should be defined.
- To connect a
DOP Header,
- Only DOP Headers in status Created can be connected to an activity.
- The DOP Header can not be connected to several activities - it's only
possible to connect a DOP Header to one activity.
- It should not be possible to connect a DOP Header that is connected/created
as a job (attribute Financial Integration should be No Integration),
against an activity.
- Posting control rule M40 should be defined.
System Effects
- The object will be connected to the new activity, as a manually connected
object.
- If appropriate, the object is updated with the project's pre-posting.
- The object will appear as a connection in the Project
Navigator/Connections
tab.
- The object will return planned (if appropriate), committed and used
cost/hours and/or progress when the activity runs the Refresh Activity
Calculation.
Window
Project
Navigator/Connections
Activity/Connections
Related Window Descriptions
N/A
Procedure
- Select the desired activity that you want to connect an object to, and
select the Connections tab.
- Select the Connect/Disconnect Object menu option.
- The Connect/Disconnect Object window will
open. Different tabs will represent
a list of objects that can be connected to activity.
- Select the objects that you wish to connect.
- Click OK to save your changes.
It is also possible to connect the object to the activity from the object window itself.
- Open the relevant object window and query for the required object.
- Right-click and point to Project Connection and select the
Connect to Activity menu option.
- Select the appropriate activity.
- Click OK to save your changes.