Generate Material Plan

Explanation

The creation of a complete material plan can be done in two steps, by first generating material plans and later on, calculation gross requirements. Or, the other way around, by first generating gross requirements and later on calculating gross requirements. Both operations can be run in one go. A recommendation is to consider the complexity of the structure, before deciding if the material plan should be generated in one or two steps.

Options for generating material plans and calculating gross requirements, are found here:

Use the Generate Material Plans option to create material plans without calculating the gross requirements for the project deliverable structure. The gross requirement calculation is optional but can also be run, as part of the creation of material plans, if the Gross Requirement Calculation check box is checked. Material plans can also be generated without calculating gross requirement. A recommendation is to review the Warning field in Material Requirements tab, before the generating material plan, as described here: Review Warnings.

Use the Calculate Gross Requirements menu option to perform the required quantity and required date calculation, which analyzes the item structure and determines when the items must be available, for the assembling of the project deliverable structure. If the Generate Material Plan check box is checked, it will generate material plans after calculating the gross requirements. A recommendation is to review the GRC Indicator field in Project Deliverables Navigator header, as described here: Review GRC Indicator. The information in the GRC Indicator, will indicate if the material plan is up-to-date or if a recalculation is needed.

Project connections on items and early finished dates on project activities, might have been modified during a project's planning phase. This affects material requirements and already generated material plans. The early finished date is used as an input for the gross requirement to calculate required date, and the required date is also passed to respective orders during the execution phase. So, it's important to keep material requirements updated with any modifications done on project connections and project activities early finished date. With the Update Project Connection check box checked, it will update those material requirements and already generated material plans. Project activities are also updated with planned cost information from already generated material plans.

 The following are not included in the above operations:

You can send the above operations into a background job. The status of the background job can be further monitored in the Background Jobs window.

Prerequisites

System Effects

A material plan record is generated by using information in the Supply Option field. The Supply Option field is found in Materials/Material Requirements tab and can have one of the following values:

Gross requirement calculates required quantities and required dates, starting with the top item and then moving down in the structure. The following is valid during the calculation of required quantities and dates:

The calculated required quantity values can be reviewed:

 The calculated required date values can be reviewed:

Window

Project Deliverables Navigator

Related Window Descriptions

Project Deliverables Navigator/Materials/Material Requirements
Project Deliverables Navigator

Procedure

Generate material plans in the Project Deliverables Navigator/Materials/Materials Requirements tab.

  1. Open the Project Deliverables Navigator/Materials/Materials Requirements tab.
  2. Right-click and then click Generate Material Plans.
  3. Optionally, also Calculate Gross Requirements, Update Project Connections and Run the process as a background job.
  4. Click OK.
  5. Open the Project Deliverables Navigator/Materials/Materials Plans tab and review the result.

Generate material plans in Project Deliverables Navigator header:

  1. Open the Project Deliverables Navigator window.
  2. Right-click and then click Calculate Gross Requirements.
  3. Select the option Generate Material Plans.
  4. Optionally, also Update Project Connections and Run the process as a background job.
  5. Click OK.
  6. Open the Project Deliverables Navigator/Materials/Materials Plans tab and review the result.