Reschedule Purchase Order Line Using Drag-and-Drop
Explanation
This activity is used to reschedule a purchase
order line using
drag-and-drop functionality from a visualization chart.
Prerequisites
- The purchase order line supply should not be
pegged to a demand.
- The purchase order line should not be
project connected.
- The new Planned Receipt Date must be a
working day.
System Effects
- The purchase order line will receive a new
Planned Receipt Date according to the
value provided in the dialog box.
Window
N/A
Related Window Descriptions
Reschedule Purchase Order Line
Related Visualization Chart Descriptions
Inventory Part Availability Planning
Procedure
- Open a visualizer enabled window and query for the site needed.
- If the Data View is displayed, click
Visualization View on the title bar.
- Right-click and select
Select Visualization.
The
Select Visualization dialog box will be
opened.
- Double-click Inventory Part Availability
Planning.
- Select the segment representing
the purchase requisition line supply you want to reschedule to a new
date.
- Click and hold the left mouse
button while moving the cursor. Release at the date to which you want
the order line to be rescheduled. The
Reschedule Purchase Order Line dialog
box will be opened.
- The date where released is defaulted as the new
Planned Receipt Date, but can be optionally edited.
- Click OK.