Send Change Request
Explanation
If you are using the EDI message function, you can send a purchase order request
message to the supplier. You also can choose to send the entire purchase order.
Prerequisites
- Basic data for the EDI message function must have been set up in IFS/Connectivity.
- You must have entered data for EDI for the applicable supplier in the
Supplier/Message
Setup.
- The purchase order must be in Released status.
- An entire purchase order should have been sent to the supplier previously.
- The supplier's part number must have been entered for
existing no part order lines.
System Effects
- The purchase order changes are sent via EDI to the supplier. On the
purchase order, the Pending Changes check box is cleared.
- If it is an internal purchase order, the message
sent will end up as an incoming change request on the supply site. If the
supply site has the Execute
Order Change Online check box
selected, the incoming change request, is processed online on the
supply site. If automatic approval is enabled you will get an instant
validation and an update on the supply site. This continues as far as possible
in multiple tiers of internal orders, if you have automatic replication and
approval through all tiers.
Without online processing all this happens in background jobs.
- For purchase order lines pegged to a customer
order line having the supply code Internal Purchase Direct or
Purchase Direct, the delivery information not saved on the purchase
order line will be taken from the pegged customer order line e.g. route,
customer calendar.
Window
Purchase Order
Purchase Orders
Related Window Descriptions
Purchase Order
Purchase Order/Misc Order Info
Purchase Orders
Send Order Change
Procedure
- Populate or query for the purchase order in question.
- Check that the purchase order is released.
- Right-click and click Send Change Request. The
Send Order Change dialog box opens. Confirm
by clicking OK.