Prepare to decomply a performed modification

Explanation

This activity is used to create a pending maintenance event for the decompliance of a modification.

When a modification is complied with, all defined actions are performed as specified. However, occasions can arise where previously performed actions need to be reversed (in other words, you need to decomply a modification). This can be performed using the Create Maintenance Event for Decompliance option. With this option, a new modification event containing the modification execution type decomply, is used to reverse the action of the modification that was previously performed.

When a modification of execution type Terminating Action leading to a part identity change is complied with, the serials assigned to and/or affected by the modification is automatically renamed to the new part number and revision. The Create Maintenance Event for Decompliance option can be used to create a pending event for the modification to reverse the performed serial rename. Once the decomplied modification event is finished, the renamed serial will be reversed back to its origin defined on the modification. This means that the renamed serial will be changed automatically and will include the old part number used before the serial was renamed. If history records were updated with the new part number of the renamed serial, these records will be updated once more to include the old part number of the serial.

Prerequisites

System Effects

Window

Modifications that can be decomplied
Define Modification
Serial Modification History List
Serial Modification History
History per Serial
Maintenance Event Summary
Reconfigure Work Scope

Related Window Descriptions

Modifications that can be decomplied
Define Modification/History
Serial Modification History List
Serial Modification History
History per Serial/Modification
Pending Maintenance Events
Component Life/Modification Compliance
Maintenance Event Summary/Modification
Reconfigure Work Scope/Modification

Procedure

General - If post maintenance checks (PMCs) exist after the modification has been complied with, you can choose to remove these PMCs immediately, or after the decomply event for this modification is completed.

Select from the following options to create a pending event for the decompliance of a modification. A decomply event can be created from any of the windows listed under Window.

Procedure 01:

  1. Open the Modifications that can be decomplied window. You can also perform this procedure from one of the windows listed under Window.
  2. Query (F3) for the serial and modification event you want to decomply.
  3. Select the relevant row, right-click and then click Create Maintenance Event for Decompliance.
  4. A message appears requesting confirmation of the event. Click OK to create a new pending event.

Procedure 02:

(Ideally, this procedure would be performed for modifications that relate to a complex MRO flow.)

  1. Open the Maintenance Event Summary window. Note that this procedure can also be performed using the Reconfigure Work Scope window.
  2. In the Work Order field, query (F3) for the work order to which the serial and modification you choose to decomply belongs.
  3. Click the Modification tab.
  4. Select the All PCW option. For example, if the required modification is included in a baseline, select this option from the Baseline Modifications area. As a result, the table in the window is populated with the modifications that are currently complied with.
  5. Select the row containing the required event, right-click, and then click Create Maintenance Event for Decompliance.
  6. A message appears requesting confirmation of the event. Click OK to create a new pending event.