Use this activity to replace the dates of the DOP order with that of the pegged orders if the pegged orders for the DOP already have been created. The start and due dates of the pegged orders might change, e.g. due to usage of IFS/Constraint Based Scheduling or manual re-planning. These new dates can and probably will differ from the dates on the DOP orders. In order to avoid getting many alarms due to these differences the activity makes it possible to substitute the purchase orders and shop orders start dates and due dates for the corresponding dates on the DOP orders. The only not updateable date is the due date on the top level DOP order, since meeting this date is the main objective for the whole DOP structure.
This activity requires that the DOP order has pegged orders.
As a result of this activity, the start date of the DOP order is set to min (supply start dates), and the due date is set to max(supply due dates).