Release DOP Header
Explanation
This activity is used to release a DOP structure manually. This is mandatory for DOP
Orders
that are not released automatically.
For a DOP Header connected to a project activity, it will not be possible to release
the DOP Header if the activity has not been released.
Prerequisites
- At least one DOP Order with a status of Created, Netted or
Unreleased
must exist. (Otherwise the Release All option will not be enabled)
- If any DOP Orders in the structure to release are serial effective,
serial numbers must be reserved for these DOP Orders.
System Effects
As a result of this activity,
- The system releases all DOP Orders which are not released in the DOP
structure. The
status will be changed to Released, which will allow you to process the
DOP orders further. For DOP orders with the Create Pegged list is set to Pegged Orders,
a pegged shop order is created if the part is manufactured and a purchase requisition
created if the part is purchased with a supply quantity that meets the remaining
demand of ther DOP order. Lot sizing rules defined for the part will be ignored. Supply orders/requisitions generated for parts with a scrap factor will
be created with a quantity higher than the DOP order quantity to cover for the
planned scrap.
- When releasing a project pegged DOP Header,
the system will create a project pegged Shop Order or Purchase
Requisition/Purchase Order, depending on the part type given for the project
part in inventory. The project pegged order is received into project inventory.
- If the Netting list has been set to Auto Netting,
quantities available in stock and/or excess quantities on existing
shop/purchase orders will be automatically reserved/pegged to the DOP order
thus reducing the quantity for which the DOP order needs to create its own
pegged supply orders.
- When releasing pegged, project-specific DOP orders, the
system will generate project-specific shop orders or purchase
requisitions/purchase orders depending on the part type. These orders will be
received into project inventory.
- A check is done before release to see if the routing is Buildable or null. If the
routing still is Plannable or has become obsolete a DOP log is created.
- An error message will pop up if user attempts to release a DOP Header
connected to an activity which is not released.
- The Lot/Batch Origin check box for DOP supplied material lines on
pegged shop orders will not be selected even though it is selected in the
product structure line.
Window
DOP Header
Related Window Descriptions
DOP Header
DOP Header/Structure
Procedure
- Select the order you want to release.
- Right-click and click Release All.
- A message will appear asking to confirm.
- Click Yes.