Perform Takt  Time Calculation

Explanation

This activity is used to calculate the takt time for defined inputs. The calculated value is saved, and can be used as the basis for additional activities such as setting the line run rate, or as the baseline takt time for comparison in the line operations analysis. 

Prerequisites

This activity has the following prerequisites:

System Effects

Window

Production Line Management

Related Window Descriptions

Production Line Management
Production Line Management/Takt Time Calc
Calculate Takt Time

Procedure

  1. Open the Production Line Management window, and right-click and then click Calculate Takt Time.
  2. The Takt Time Demand sample start and the end dates appear in the dialog box according to the default  scheduling horizon. You can manually change this date in the dialog box.
  3. Click OK.