Explanation

Use this activity to perform netting processes for the selected order and all its lower orders. It is also possible to perform re-netting when the quantity of the structure is changed after the release; you can also re-net after canceling netting relations.

Netting is performed in the following sequence:

For DOP orders where the DOP header is connected to a project, and where the Create Pegged option is set to Pegged Orders, netting is allowed only from the project inventory. If the Create Pegged option is set to No Pegged Orders, netting is allowed only from standard inventory. 

For project connected DOP orders, netting is performed in the following sequence:

Prerequisites

This activity requires that:

System Effects

As a result of this activity:

Window

DOP Header
DOP Order

Related Window Descriptions

DOP Header
DOP Header/Structure

DOP Order
DOP Order/Detail

Procedure

  1. Open the DOP Header/Structure or DOP Order window.
  2. Select the DOP order for the branch, to be used for netting.
  3. Right-click, point to Net and then click Branch.
  4. A message appears inquiring whether you want to net the branch DOP header. Click Yes to confirm.