Specify Step Update Budget

Explanation

This activity is used to include a step of the Update Budget step type in a selected cost allocation procedure.

Prerequisites

In order to perform this activity, a cost allocation procedure of the Budget allocation type should exist.

System Effects

As a result of this activity, the destination budget of the cost allocation procedure will be updated with the allocation results.

Window

PCA Step Definition

Related Window Descriptions

PCA Step Definition

Procedure

To specify step type Update Budget:

  1. Open the PCA Step Definition and search for the procedure for which you want to enter the step.
  2. Create a new record in the table.
  3. Enter a value in the Seq No field to specify the sequence.
  4. Enter an ID for the step in the Step ID field.
  5. Select Update Budget for the Step Type field.
  6. Save the information.