Plan Work Lists per Preventive Maintenance Plan Line

Explanation

Use this activity to  plan work lists manually by altering planned start and finish dates of the work list items that are registered in PM Action/Jobs and Work List dialog for a single occurrence in the preventive maintenance plan (PM plan).

Note:

Prerequisites

 

System Effects

Window

PM Action

Related Window Descriptions

PM Action 
PM Action/Maintenance Plan
Jobs and Work Lists

Procedure

  1. Open the PM Action window, and query for the required PM action.
  2. Click the Maintenance Plan tab.
  3. Select the PM plan line for which you want to schedule the jobs and work lists.
  4. Right-click and then click Jobs and Work Lists. The Jobs and Work Lists dialog box opens.
  5. Change the value in the Date From field for the jobs listed in the header.
  6. Change the value in the Date From field for each work list line found in the table.
  7. Click OK.