Manually Generate Work Order
Explanation
Use this activity to manually generate work orders directly
from PM actions. You can do that if you need to
generate a work order for a certain PM action,
regardless of generation conditions. If you want to have several progressing WO
at the same time or generate any line, then you need to set the Performed
Value Based and Performed Date Based to No.
Prerequisites
The PM action should be active and valid.
System Effects
As a result of this activity, the current PM action will
generate a work order. It will then be available for further preparations along with other regular work orders.
Window
PM Action
Related Window Descriptions
PM Action
Procedure
- Open the PM Action window and query for an existing record (F3).
- Right-click any where on the window and click Generate Work Order.
- If you want to manually generate a work
order from a calendar plan or condition plan click the Maintenance Plan tab for
the PM action,
select the required line, right-click and click Generate Work Order.
- If Performed Date Based is Yes then it is only allowed to
manually generate next due calendar line and if Performed Value Based
is Yes, then it is only allowed to manually generate next due condition
line with a generation value.