Connect Resources to Work List
Explanation
Use this activity to plan resources on work list for work task template. Here, you
can plan the persons and tool/equipments you expect to need to perform the work.
Prerequisites
- Current work task template
Work List tab
retrieved, for a work task template.
- Persons and Tool/Equipment to be
defined and connected to a Resource Group.
System Effects
As a result of this activity, resources lines are connected to the work list.
When you then decide to link the work task template to a PM action or a work order, all
resources lines will be copied.
Window
Work Task
Template
Related Window Descriptions
Work Task Template
Work Task Template/Work List/Resources
Procedure
- Open the Work Task Template window, and
query for an existing work task template.
- Click the Work List/Resources tab and create a new record (F5).
- Enter a value in the Demand Type field.
Use the dropdown menu to select a suitable value.
- Enter the resources group for the work list in the Resources Group.
- Enter the quantity (planned men or number of tool/equipments) required in the Planned Quantity field.
- Enter any other optional information in the
Remark
field.
- Save the information (F12).
Optional
- Click the
Valid for
Sites tab and select the applicable site record.
- Click the
Valid for
Sites/Resources tab and enter the resource in the Resource ID
field. Note: A Resource ID can only be entered when the
planned quantity is 1 and vice versa.
- If you want to invoice the price of the resources to a customer, enter
the Sales Part No.
- Save the information (F12).
Note: Additionally, the Additional Qualification could be
defined on resource lines with Person demand type.