Connect PM Action
Explanation
Use this activity to link PM Actions into structures. You can do that by
selecting a superior PM Action, and then connecting underlying PM Actions. PM structures
are useful when a job involves several maintenance organizations and you want a work order created for
each maintenance organization.
Prerequisites
- The PM action to be connected must have been entered in IFS/Preventive and
Corrective Maintenance.
- The PM action to be connected should not be in any replacement
structure, i.e., it should not be a PM action which replaces other PM
actions or gets replaced by some
other PM action.
- The PM action to be connected should have a valid revision in either the
Preliminary or Active status.
System Effects
As a result of this activity, a PM Action is included in a structure.
The following effects can also be observed depending on the information
specified in the superior PM:
- When a PM structure is created with or without Calendar generation
details defined in the superior PM, the calendar details defined in the
underlying PMs will be replaced with the corresponding details from the
superior PM.
- When a PM structure is created with or without Event generation details
defined in the superior PM, the event details defined in the underlying PMs
will be replaced with the corresponding details from the superior PM.
- When a PM structure is created with or without Criteria generation
details defined in the superior PM, the same or different criteria details
defined in the underlying PMs will be removed. Once criteria on the superior
PM is satisfied and Condition Generation is performed, Work Orders will be
generated for all PMs of the structure. Further a Work Order Structure will be
created.
Window
PM Action
Related Window Descriptions
Connections for PM Action
Procedure
- Open the PM Action window and query for an
existing PM Action.
- Right-click and click Connections. The
Connections for PM Action
window appears.
- Create a new record (F5).
- In the Connected PM No field, use the List of Values to select a PM
Action.
- In the Revision field, use the List of Values
to change the revision of the selected PM action if necessary.
- Save the information (F12).