Action for Shop Order

[About Material Requirements Planning] [About Project Material Requirements Planning]

[To Make to Stock Planning] [To Production Schedule Planning]

Usage

Use this dialog box to do actions that MRP propose for a specific purchase order line or shop order. Using this dialog box it is possible to do actions for MRP Messages like Early Order, Late Order, Remove Order, Supply is Past Due, Min Order Qty > Lot Size, Order > Max Lot Size, Order After Horizon and Order Not Multiple.

In the upper part of the dialog box, there is information about the MRP proposal and planning data for the part.

In the middle part of the dialog box, there is information about the shop order or the purchase order line.

In the lower part of the dialog box, you can enter an action note, and the note will be visible for the order until the purchase order line is cancelled or closed.

Activity Diagrams

Perform MRP

Activities

Actions for Order