Specify Scheduling Settings for Maintenance Planning Board
Explanation
This activity is used to define the different default time frames used by the
Maintenance Planning Board (MPB) when scheduling work tasks/work lists for a site.
Prerequisites
- This activity requires that the site is added in Maintenance
Planning Board Basic Data window.
System Effects
As a result of this activity, Site can be schedule inside MPB and the values you specify are used by the
MPB to schedule work tasks/work lists.
Window
Basic Data for Maintenance Planning Board
Related Window Descriptions
Basic
Data for Maintenance Planning Board
Procedure
- Open the Maintenance Planning Board Basic Data
window and query for the site you want to specify scheduling settings.
- Select the Enable MPB Scheduling check box.
- In the Scheduling Horizon field, enter the number of days that
the MPB should consider when scheduling. The default value is 365. You can set any value up
to five years but shorter time frames will provide better performance.
- In the Scheduling Start Point (Hours from Present Time) field,
enter a default start time for the first work task in the schedule. This
optional value is set to 8 hours by default.
- Save the information.