Calculate Lead Time for Routing
Explanation
Use this activity to calculate a part’s manufacturing lead time. The
manufacturing lead time is calculated from the default routing and lot size of
the part. It considers the setup, move, operation times, and the efficiency
factor entered for the operation. The total
lead time will be reduced to reflect the operation overlapping if the overlap value
is defined for the routing.
Prerequisites
This activity requires a part for which a routing is defined.
System Effects
As a result of this activity:
- The system changes the manufacturing lead-time
values on this routing alternate.
- If the routing alternate is '*', the system also updates the lead
times found on the
Inventory Part/Manufacturing tab and on the
Inventory Part/Acquisition tab.
Window
Routings
Routing Alternates
Related Window Descriptions
Lead Time Calculation
Routing
Routings/Routings
Routing Alternates
Procedure
- Open the Routing window and display the part by populating or by making a selective query.
- Click the
Routings tab.
- Right-click and then click Calculate
Lead Time. The
Lead Time Calculation
dialog box will be opened.
- In the Update Options list, click a suitable option. Possible
values are: Update, Do not Update and Update Also
Expected.
- Click one of the options under Capacity. The available options
are Average and Demonstrated.
- Under Lead Time Calculation Basis, click a suitable option to
determine the lead time for the part.
- Click OK.