Enter Master Schedule Level 0 Forecast

Explanation

This activity is used to enter forecasts for level 0 parts.

Prerequisites

This activity requires that the part must have been registered as a level 0 part before you can enter the forecast.

System Effects

As a result of this activity, the system automatically transfers the forecast you enter on level 0 to level 1 when the disaggregation process is performed.

Window

MS Level 0 Part

Related Window Descriptions

MS Level 0 Part
MS Level 0 Part/Register Forecast

Procedure

  1. Search for the relevant MS level 0 part and click the Register Forecast tab.
  2. In the MS Set list, select the master schedule set for which you want to enter forecasts. If the required MS set is not available in the list, create a new record and use the List of Values to select from available MS sets and Save.
  3. Create a new record in the table below.
  4. In the Forecast Date field, enter the date when the forecast will be valid. The system determines if the date is within or outside of the time limit.
  5. Enter the forecast for the part in the Forecast field.
  6. Repeat steps 3-5 for each forecast you want to register.
  7. Save the information. When you save the forecast, the period is displayed.