Define RRP Unique Work Centers
Explanation
This activity is used to enter work centers to be used solely by resource
requirements planning (RRP). The work centers with work center code
Resource Requirement Planning are usable only in resource planning.
The information you enter for RRP-unique work centers is used when you work
with resource requirements planning.
Prerequisites
There are no prerequisites for this activity.
System Effects
As a result of this activity, the system creates a work center solely used by
RRP, with work center code Resource Requirement Planning.
Window
Work Center
Related Window Descriptions
Work Center
Work Center/RRP Capacity
Procedure
- Create a new record.
- Enter the short code of the work center in the
Work Center
field. This code can
consist of up to 5 alphanumeric characters. Enter a description for the work
center.
- In the Site field, specify the site at which the work center is to
be used. Use
the List of Values to select from
available sites.
- Specify the work center's queue time.
- In the Work Center Code
field, select the value Resource Requirement Planning.
- In the Calendar ID field, enter the calendar to use. Use
the List of Values to select from
available calendars.
- Specify the utilization of the work center in the Utilization
field. The default value is 100.
- Specify the work center's unit of measure. Use
the List of Values to select from
available units of measure.
-
In the
Validity field, select Active.
- Save.