Define Master Schedule Level 0 Part

Explanation

Use this activity to register a part as master scheduling level 0 part.

Prerequisites

System Effects

As a result of this activity, the part is registered as a master schedule level 0 part.

Window

MS Level 0 Part

Related Window Descriptions

MS Level 0 Part

Procedure

  1. Open the MS Level 0 Part window.
  2. Create a new record.
  3. In the Part No field, enter the part number for the part you want to register as a MS level 0 part or use the List of Values to select from available parts.
  4. If you want to plan a part which is project connected, select values in the PNG and Activity ID fields.