Select Operation(s) and Create Operation Block

Explanation

Use this activity to select one or several operations to include in a new operation block.

Prerequisites

System Effects

As a result of this activity a new operation block will be created and the selected operations will be connected to the operation block.

If a Preferred Resource is specified this value will also be set as the preferred resource on the operation(s) connected to the operation block which will trigger a rescheduling of the operation(s).

Window

Shop Order
Shop Order Operations
Shop Floor Workbench

Related Window Descriptions

Connect Operation(s) to Operation Block
Shop Order/Operations
Shop Order Operations
Shop Floor Workbench

Related Visualization Chart Descriptions

Shop Order Machine Load
Shop Order Labor Load
Machine Operation Load In Standard Hours
Labor Operation Load In Standard Hours

Procedure

Shop Floor Workbench window

  1. Open the Shop Floor Workbench window. If Reporting Mode has been set to Employee Reporting on the used site an employee or team must have been entered in the Enter As dialog box.
  2. Click Refresh. The operations will be displayed according to the filter that is being used.
  3. Select the operation(s) that you want to connect to an operation block, right-click, point to Operation Block and then click Connect. The Connect Operation(s) to Operation Block dialog box opens with the selected operations populated in the table section.
  4. Select the Connected check box for the operations you want to include in the operation block.
  5. Select Create New Operation Block.
  6. Optionally specify the work center resource on which you prefer the operations in the operation block to be performed. Use the List of Values to select from available work center resources.
  7. Click OK.

Shop Order/Operations or Shop Order Operations window

  1. Open the appropriate window and search for the operations to connect to an operation block.
  2. Select the operation(s), right-click, point to Operation Block and then click Connect. The Connect Operation(s) to Operation Block dialog box opens with the selected operations populated in the table section.
  3. Select the Connected check box for the operations you want to include in the operation block.
  4. Select Create New Operation Block.
  5. Optionally specify the work center resource on which you prefer the operations in the operation block to be performed. Use the List of Values to select from available work center resources.
  6. Click OK.

Shop Order Machine Load, Shop Order Labor Load, Machine Operation Load In Standard Hours or Labor Operation Load In Standard Hours visualization chart

  1. Open a visualizer enabled window and query for the site needed.
  2. If the Data View is displayed, click Visualization View on the title bar.
  3. Right-click and click Select Visualization. The Select Visualization dialog box is opened.
  4. Double-click Shop Order Machine Load, Shop Order Labor Load, Machine Operation Load In Standard Hours or Labor Operation Load In Standard Hours .
  5. In Shop Order Machine Load, Shop Order Labor Load charts, right-click and click Y-Axis/Shop Order Operation.
  6. Select the inner segment representing the shop order operation(s) you want to connect to an operation block, right-click, point to Operation Block and then click Connect. The Connect Operation(s) to Operation Block dialog box opens with the selected operations populated in the table section.
  7. Select the Connected check box for the operations you want to include in the operation block.
  8. Select Create New Operation Block.
  9. Optionally specify the work center resource on which you prefer the operations in the operation block to be performed. Use the List of Values to select from available work center resources.
  10. Click OK.