Forward Schedule Block Operations in Parallel

Explanation

Use this activity to forward schedule shop order operations connected to an operation block parallel to each others from a given start date/time.

Prerequisites

System Effects

Window

Operation Block
Operation Blocks
Shop Order
Shop Order Operations
Shop Floor Workbench

Related Window Descriptions

Schedule Operation Block
Operation Block
Operation Blocks
Connect Operation(s) to Operation Block
Shop Order/Operations
Shop Order Operations
Shop Floor Workbench

Related Visualization Chart Descriptions

Shop Order Machine Load
Shop Order Labor Load
Machine Operation Load In Standard Hours
Labor Operation Load In Standard Hours

Procedure

From Operation Block and Operation Blocks windows:

  1. Search for the operation block you wish to schedule.
  2. Right-click and click Schedule Operation Block. The Schedule Operation Block dialog box appears.
  3. Select the Forward Scheduling option.
  4. Optionally, use the List of Values in the Preceding Block field to select which operation block this block should succeed. The Start Date will be set the same as the preceding block's finish date, and the Preferred Resource will be set the same as the preferred resource of the selected preceding block.
  5. Verify or enter the date/time on which you want the operations in the operation block to start in the Start Date field.
  6. Verify or enter the resource on which you want the operations to be scheduled in the Preferred Resource field. Use the List of Values to select from available work center resources.
  7. Select the Schedule in Parallel option.
  8. If you want to avoid slack between operations preceding the block operation on the same shop order when rescheduled to a later date/time, select the Compress Operations check box.
  9. Click OK.

From the Connect Operation(s) to Operation Block dialog box:

  1. Select the Schedule Operation Block check box and click OK, the Schedule Operation Block dialog box appears.
  2. Select the Forward Scheduling option.
  3. Optionally, use the List of Values in the Preceding Block field to select which operation block this block should succeed. The Start Date will be set the same as the preceding block's finish date, and the Preferred Resource will be set the same as the preferred resource of the selected preceding block.
  4. Verify or enter the date/time on which you want the operations in the operation block to start in the Start Date field.
  5. Verify or enter the resource on which you want the operations to be scheduled in the Preferred Resource field. Use the List of Values to select from available work center resources.
  6. Select the Schedule in Parallel option.
  7. If you want to avoid slack between operations preceding the block operation on the same shop order when rescheduled to a later date/time, select the Compress Operations check box..
  8. Click OK.

From Shop Order Operations, Shop Order/Operations and Shop Floor Workbench windows:

  1. Search for the shop order operation connected to operation block you wish to schedule.
  2. Right-click, point to Operation Block and then click Schedule. The Schedule Operation Block dialog box appears.
  3. Select the Forward Scheduling option.
  4. Optionally, use the List of Values in the Preceding Block field to select which operation block this block should succeed. The Start Date will be set the same as the preceding block's finish date, and the Preferred Resource will be set the same as the preferred resource of the selected preceding block.
  5. Verify or enter the date/time on which you want the operations in the operation block to start in the Start Date field.
  6. Verify or enter the resource on which you want the operations to be scheduled in the Preferred Resource field. Use the List of Values to select from available work center resources.
  7. Select the Schedule in Parallel option.
  8. If you want to avoid slack between operations preceding the block operation on the same shop order when rescheduled to a later date/time, select the Compress Operations check box..
  9. Click OK.

From a visualizer chart:

  1. Open a visualizer enabled window and query for the site needed.
  2. If the Data View is displayed, click Visualization View on the title bar.
  3. Right-click and click Select Visualization. The Select Visualization dialog box is opened.
  4. Double-click Machine Operation Load in Standard Hours, Labor Operation Load in Standard Hours, Shop Order Machine Load or Shop Order Labor Load.
  5. Select the bar/segment representing the shop order operation(s) connected to operation block you want to schedule, right-click, point to Operation Block and then click Schedule. The Schedule Operation Block dialog box appears.
  6. Select the Forward Scheduling option.
  7. Optionally, use the List of Values in the Preceding Block field to select which operation block this block should succeed. The Start Date will be set the same as the preceding block's finish date, and the Preferred Resource will be set the same as the preferred resource of the selected preceding block.
  8. Verify or enter the date/time on which you want the operations in the operation block to start in the Start Date field.
  9. Verify or enter the resource on which you want the operations to be scheduled in the Preferred Resource field. Use the List of Values to select from available work center resources.
  10. Select the Schedule in Parallel option.
  11. If you want to avoid slack between operations preceding the block operation on the same shop order when rescheduled to a later date/time, select the Compress Operations check box..
  12. Click OK.