Reschedule Shop Order Material Line Using Drag-and-Drop
Explanation
This activity is used to reschedule a shop order
material line and optionally the shop order operation requiring the material using
drag-and-drop functionality from a visualization chart.
Prerequisites
N/A
System Effects
- The shop order material line will receive a new
Required Date according to the
value provided in the dialog box.
- If the check box Reschedule Shop Order
Operation(s) is not selected and the new Required Date is later
than the Finish Date of the operation which to the material line is
connected, the operation connection will be removed.
- If the check box Reschedule Shop Order
Operation(s) is not selected, the new Required Date may not be
later than the Finish Date of the shop order.
If the Reschedule Shop Order Operation(s)
check box is selected:
- Schedule Direction for the operation which
to the material line is connected will be set to Forward Scheduling and the operation will be rescheduled to start the first
available work date/time from the given value. If the material line is not
connected to any operation the first operation will be considered.
- Operations parallel to, and succeeding the rescheduled operation will
also be set to Forward Scheduling and rescheduled.
If the new Required Date is later than the
original date, the Compress Operations check box can be selected. If
selected operations preceding the rescheduled operation will be set to
Backwards Scheduling
and rescheduled with a Finish Date
adjacent to the rescheduled
operations new Start Date.
- If the site is CBS server enabled, it is only possible to change the
Required Date of the material. Rescheduling of operations ( with or
without compress operations ) is not possible as scheduling individual
operations will be handled by CBS server logic and date required is not an
input for operation scheduling. For CBS , Material cumulative lead time,
scheduling capacity setting in the inventory part , supplies and demand
situations for the part will determine the material constraint when
scheduling.
Window
N/A
Related Window Descriptions
Reschedule Shop Order Material Line
Related Visualization Chart Descriptions
Inventory Part Availability Planning
Procedure
- Open a visualizer enabled window and query for the site needed.
- If the Data View is displayed, click
Visualization View on the title bar.
- Right-click and select
Select Visualization.
The
Select Visualization dialog box will be
opened.
- Double-click Inventory Part Availability
Planning.
- Select the segment representing
the shop order material line demand you want to reschedule to a new
date.
- Click and hold the left mouse
button while moving the cursor. Release at the date to which you want
the material line to be rescheduled. The
Reschedule Shop
Order Material Line dialog
box will be opened.
- The date where released is defaulted as the new
Required Date, but can be optionally edited.
- Optionally select the Reschedule Shop Order
Operation(s) check box to reschedule also the operation which to the
material line is connected.
- Optionally select the Compress Operations
check box if you want to avoid slack between the operations.
- Click OK.