Mass Update Shop Order Routings
Explanation
This activity is used to update routings on all shop orders sharing a selected part number, routing type, revision and alternate. You can update to the same revision and alternate, or change to another buildable revision and alternate.
Prerequisites
- To perform an update, there should be at least one shop order satisfying the selection criteria.
- A mass update only affects shop orders in the Planned and Released
status.
- Shop Orders with scheduling direction Manual Scheduling will not
be updated.
- Mass update is not allowed for configured parts.
System Effects
As a result of this activity, the operations on the selected shop orders are removed and then copied again from the routings. This is because the operations of the routing may not be the same as when the shop order was created. This also means that the material connected to
the operations will lose their operation number in the process. This can be resolved by
also running mass update shop order structures via the Mass Update Shop Order Structures dialog box afterwards. Then the material will get their operation numbers back.
Window
Mass Update Shop Order Routings
Related Window Descriptions
Mass Update Shop Order Routings
Mass Update Shop Order Structures
Procedure
- Open the Mass Update Shop Order Routings dialog box.
- Enter the required site in the Site field or click List to select a site from the List of Values.
- In the Part No field, enter the part number of the shop orders to
be updated or click List to select the required part number from the List of Values.
- Select the required routing type from the Routing Type list.
- If you want to update only the planned orders, clear the Update Released Shop Orders
check box.
- In the Revision field and Alternate field in the From area, enter the revision and alternate of shop orders to be updated, or click
List to select the relevant values.
- In the Revision field and Alternate field in the To area, enter the revision and alternate to which the shop orders should be updated to, or click
List to select the relevant values.
- Click OK.
- Check the background job for any warnings or information messages.