Change Work Center or Resource
Explanation
Use this activity to change the work center or resource attached to the particular shop order operation.
Prerequisites
This activity requires to have allocated work center and resources to the shop order operation.
System Effects
As a result of this activity, current work center will be changed with the new work center and preferred resources.
Window
Shop Floor Workbench
Related Window Descriptions
Change Work Center or Resource
Shop Floor Workbench
Procedure
- Select the Employee ID or Team ID in the Enter As dialog box to enter to the Shop Floor Workbench window.
- Select the needed shop order operation line, right-click and select Change Work Center or Resource.
- In the Change Work Center or Resource dialog box select the new work center and preferred resource and select OK.
- Existing work center & resource will be replaced with the new work center and allocated resource.