Change Work Center
Explanation
Use this activity to re-plan the operation to another work center.
Prerequisites
An active, internal work center must exist on the same site.
System Effects
As a result of this activity the operation is rescheduled on the new work
center.
Window
Shop Floor Workbench
Related Window Descriptions
Change Work Center or Resource
Procedure
- Open the Shop Floor Workbench window. If Reporting Mode
has been set to Employee Reporting on the used site an employee or
team must have been entered in the Enter As dialog box.
- Click Refresh. The operations will be displayed according to the filter
that is being used.
- Select the operation line for which you want to change the work center
and click the Change WC option, or right-click and select the
corresponding option.
- In the New Work Center field, use List of Values to select the
work center on which you plan to execute the operation.
- Click OK.