Specify Maintenance Import Interval

Explanation

Use this activity to schedule the importation of work orders from IFS/Maintenance. These work orders are considered as resource breaks within Constraint Based Scheduling (CBS). Neither maintenance break dates and times nor break times can be modified.

Prerequisites

This activity has the following prerequisites:

The work orders that will be imported as resource breaks has to fulfill the following constraints:

System Effects

As a result of this activity:

Window

Maintenance Import

Related Window Descriptions

Maintenance Import

Procedure

  1. Open the Maintenance Import dialog box.
  2. Enter values in the Site, Work Center No, Resource ID, Begin Date Offset, and End Date Offset fields according to the work orders that you want to import.
  3. Click Schedule and follow the steps in the assistant.