Import Maintenance Workload

Explanation

This activity is used to import tasks from IFS/Maintenance. These tasks are considered resource breaks within CBS. Neither Maintenance break dates and times nor CBS break times can be modified.

Prerequisites

This activity has the following prerequisites:

The tasks that will be imported as resource breaks has to fulfill the following constraints:

System Effects

As a result of this activity:

Window

Maintenance Import

Related Window Descriptions

Maintenance Import

Procedure A

  1. In the Site field, specify the site to which you want to import the maintenance tasks. Use List to select from available sites.
  2. In the Work Center No field, specify for which work center you want to import maintenance tasks. Use List to select from available work centers. If you specify no work center, tasks for all work centers are imported. As an alternative to specifying the work center number, you can specify the name of the tool that will be used for importing Maintenance task in the Tool ID field. If you specify no tool ID, tasks for all tool IDs are imported.
  3. In the Resource ID field, specify for which resource you want to import maintenance tasks. Click List to select from available resources. If you specify no resource ID, tasks for all resource IDs are imported. As an alternative to specifying the resource, you have the option of specifying the name of the tool instance in the Tool Instance field. If you specify no tool instance, tasks for all tool instances are imported. specify no tool ID,tasks for all tool IDs are imported.
  4. In the Begin Date Offset and End Date Offset fields, specify the offset in number of days.
  5. specify no tool ID, tasks for all tool IDs are imported.
  6. Click OK.

Procedure B

Click Schedule and follow the steps in the wizard.