Create/Modify Resource Breaks
Explanation
This activity is used to create or modify a resource break. Resource breaks
are taken into account only when orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order
Infinite Scheduler.
Prerequisites
This activity requires the existence of a site to which you can connect the resource
break. Furthermore, you must have defined the resource to which the resource break
applies.
System Effects
- If you create a new resource break, it will be in Proposed state.
It cannot be loaded to the Advanced Planning Board (APB) while it is in this state.
- If you modify an existing resource break which is in Approved or
Scheduled state, its state changes to Unscheduled.
Window
Resource Break
Advanced Planning Board
Related Window Descriptions
Resource Break
Advanced Planning Board
Procedure
- In the
Resource Break window, select New to create a
new resource break. Alternatively, query for an existing one.
- For a new resource break, enter the break number in the Break No field, or let the
system define one automatically.
- Enter or modify a description for the resource break in the Break Description field.
- For a new resource break, specify the site at which the resource break will
be used in the
Site field. Use the List of Values to select from available sites. The selected site
may not be modified.
- For a new resource break, accept the default break type setting of Manual. The break
type cannot be modified.
- In the Work Order field, accept the blank setting or the default value.This number cannot be specified for a manual break. It is system-supplied for a
break that has been imported from IFS/Maintenance.
- Enter or modify the break duration in the Break Duration field. This value is defined in
hours.
- Enter or modify the range in which the resource break may be scheduled in the
Begin Date
Range and End Date Range fields. The range must be large enough to accommodate the break
duration.
- Perform one or more of these steps:
- Enter or modify the work center resources for the resource break in the
Work
Center Resources tab.
- Enter or modify the tool instances for the resource break in the
Tools
tab.
- Enter or modify the labor resources for the resource break in the
Person
tab. Only persons in labor classes with Capacity Calc Base
set to Individuals will be applicable. For labor classes
with Capacity Calc Base set to Group,
you should modify the capacity instead of creating a resource break.
- Click Save to save the new or modified resource break.
- Whenever desired, change the status of the resource break by
right-clicking and then clicking one of the available
options as appropriate. These options include Approve, Discard,
Confirm, Schedule, Unschedule, and
Complete.
Note: For resource breaks in non-Constraint
Based Scheduling sites, the only options available are Approve, Discard,
Reject and Complete.
Creating a resource break using the Advanced Planning Board:
- Load the Advanced Planning Board and click the
Activities tab.
- Select the Resource Breaks node, right-click and
then click New Child. This will open the Create dialog
box.
- Enter a name for the resource break in the Name
field.
- Click Resource Break. A new resource break
object will be created under the Resource Breaks node and the
Resource
Break window appears. The resource break
will be in Incomplete state.
- In the Show Status tab, enter
appropriate dates in the Need Date and EPST fields.
- Click the Show Contents tab and enter the break
duration in the Duration Time field.
- Enter a description in the Description field.
- Click the Show Assignment tab and
then click New Role.
- Drag and drop a resource from the Master
Data tab of the Advanced Planning Board to the Assigned
Resource field. You may add more than one role and a resource if
necessary.
- Drag and drop the resource break object into the
object table area.
- Select the object in the object table area,
right-click and then click Scheduling.
- In the Change Schedule dialog box
that appears, select the appropriate option in the When rescheduling this
area and then click OK.