Complete Resource Breaks
Explanation
This activity is used to complete a resource break which is in Scheduled
state. The status of the break changes to Finished. A resource break in
Finished state has no effect on the shop order schedule. Resource breaks are taken
into account only when the orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order Infinite
Scheduler.
Prerequisites
A resource break having Scheduled status must exist.
System Effects
As a result of this activity:
- the status of the resource break changes from Scheduled
to Finished.
- if the break belongs to a CBS site, it
will be removed from the Scheduling Server.
- if the break belongs to an Advanced Planning Board (APB) site, it will not be loaded when the APB
is used.
- the capacity which was booked by the resource break becomes available
for scheduling other objects through the APB or CBS.
Window
Resource Break
Related Window Descriptions
Resource Break
Resource Breaks
Procedure
- Populate the window.
- Select the resource break(s) you want to complete.
- Right-click and then click
Complete. The status of the selected break(s) changes to Finished.