Add Shop Order Component

Explanation

This activity is used to add a component part that is not registered in the structure of the parent part, e.g., material that is needed only for this shop order. 

Prerequisites

This activity requires the existence of a shop order.

System Effects

As a result of this activity, the system adds a component part to a specific shop order. This change does not affect the entire part structure.

If the component part has planning method K (Blow Through), the component will directly after save be replaced with components from the K parts structure. Component scrap and scrap factor for the K part will not be considered when the part is replaced with its component.

Window

Shop Order
MRO Shop Order
Disposition Shop Order

Related Window Descriptions

Shop Order
Shop Order/Materials
MRO Shop Order
MRO Shop Order/Materials
Disposition Shop Order/Materials
Disposition Shop Order

Procedure

  1. Create a new record on the Materials tab.
  2. Enter a line number in the Line Item No field.
  3. In the Component Part field, enter the number of the component you want to add. Use the List of Values to select from available parts.
  4. In the Qty per Assembly field, enter the quantity of the components needed to manufacture one parent part.
  5. In the Component Scrap and Scrap Factor fields, enter the fixed scrap quantity and scrap factor. The system calculates the total amount needed and displays the result in the Component Qty Required field.
  6. In the Service Type field enter a service type. Use the List of values to select a suitable value and the component repair order line connected to service type(s) will be listed.
    Note: This field is enabled only if the shop order is a repair shop order and originated from a CRO line.
  7. Save.