Specify Warehouse Worker Information

Explanation

The warehouse worker is the person who carries out the warehouse tasks; each worker must be entered in the system, together with information about his or her task types and location groups. Each worker is connected to a work schedule that is defined in Calendar.

The warehouse worker is connected to a person entered in Person in IFS/Enterprise. All the personal data, such as name and address, is entered. In addition, the following information needs to be specified: the worker's task types, how much of the worker's time that should be spent performing the tasks, and his efficiency rating. The warehouse worker also must be connected to the location groups where he can work.

This information is used both for warehouse planning and warehouse management. The planning functionality includes the possibility to view the total available work time and compare it to the work load. This kind of information can be seen in Workload per Location Group and in graphical form Work Load per Location Group Graph.

The warehouse management functionality uses the warehouse worker information when tasks are assigned; for example, the system decides which tasks can be assigned to a specific worker.

Prerequisites

System Effects

A warehouse worker is created. According to the worker's task types and location groups, he can now be assigned to his allowed warehouse tasks and he can also receive new tasks in Warehouse Manager Task Planning.

Window

Warehouse Task Basic Data

Related Window Descriptions

Warehouse Task Basic Data/Warehouse Worker
Warehouse Task Basic Data/Warehouse Worker/Task Type
Warehouse Task Basic Data/Warehouse Worker/Location Group

Procedure

  1. Open the Warehouse Task Basic Data window and then click the Warehouse Worker tab.
  2. Select the upper part of the tab, and then click New.
  3. Enter the worker ID. You can select it from the List of Values. The worker description will be automatically entered.
  4. Enter the site, worker group, and calendar for the warehouse worker. These can be selected from the List of Values.
  5. In the Valid from Date field, enter the date when the worker information will be valid. If you know that the warehouse worker information is only valid for a certain period, you can set the end date in the corresponding field.
  6. Save the information.
  7. Click the Task Type tab and create a new record.
  8. From the list box, select the task type that the worker will perform.
  9. Enter the effective time share and effective efficiency rate in the corresponding columns.
  10. Select the status of the task type from the list box and save the information.
  11. Click the Location Group tab and create a new record.
  12. Enter the location group for the worker, either from the List of Values or manually. The location group description will be entered automatically.
  13. Enter the actual time share in the Actual Time Share column.
  14. Select the status of the task type from the list box and save the information.