Get Warehouse Task - Transport
Explanation
If a transport task is activated in Warehouse
Task Basic Data/Warehouse Task
Type Setup tab, a warehouse task is generated when a transport task is created.
If that is the case, it is possible to execute the transport task in warehousing as well.
Warehouse tasks can be assigned to a warehouse worker either before that task
has been started or when it is started.
The warehouse tasks are ordered by their latest start date and
priority. If a task has been assigned to a warehouse worker before it was started, this
task is prioritized over other tasks. When a new task is started, it is assigned to a
specific warehouse worker; depending on the task types and the location groups, he can
work on the next task selected.
Prerequisites
- The warehouse task type setup must be set for the specific task
type. The task must have Active status in
Warehouse Task Basic Data/Warehouse Task Type Setup tab.
- The warehouse worker must be entered for the specified site in
Warehouse Task Basic Data/Warehouse
Worker tab. Also, the task type and location group must be entered for the
worker and be activated in both Warehouse
Task Basic Data/Warehouse Worker/Task Type tab and
Warehouse Task Basic Data/Warehouse
Worker/Location Group.
- A warehouse task must have been created. It is the task type setup
that decides whether a task will be created. You can see if there are any available tasks
in Warehouse Tasks. Also, the task must have Released
status.
System Effects
When a warehouse task has been selected, the status of the task
is changed to Started, which means that the transport task is being performed.
Window
My Warehouse
Task
Related Window Descriptions
My Warehouse Task
Procedure
From the My Warehouse Task window:
- Open the My Warehouse Task window
and query for the required worker ID.
- Populate or query for the required worker ID. All tasks in the Released or Started
status are displayed in the top table.
- If you need to start the next available task, click
Start
Next. It is possible to start a new task only if you do not have any
task in the status Started.
- If you wish to start selected task, click Start Selected.
- To complete a task, click Complete.
Note: After completing a task it is possible to start a new task and
the completed task will disappear from the task list.
- If there are no tasks available in the queue, it
is possible click New and you can assign a suitable task. The New
option is enabled only if there are no tasks available in the queue.
- If you need to view by the task type: Click Search and the
Search Task dialog box is displayed.
Then click the Filter by Task Type option, and select the required task type from the
Task Type list.
- If you need to view by the location group: Click
Search and the Search Task dialog is displayed.
Then click the Filter by Location Group option, and enter or select
the required location group using the List of Value in the Location Group
field.