Set a Maintenance Program Active
Explanation
This activity is used to activate a maintenance program. Only one revision of
a maintenance program can be active at any given time. If a revision of the
maintenance program is already in the Active status, it will be set to
the Obsolete status when you choose to activate another revision of the
maintenance program.
Serials can only be connected to active maintenance
programs. When a new revision of a maintenance program is activated, all serials
(that are not locked) connected to the old maintenance program revision will be reconnected
to the new revision. If there exists locked serials connected to the old
maintenance program revision, they will not be connected to the new revision of the
maintenance program when it is activated. You must unlock a serial to be able
to connect an active maintenance program to the serial.
Note that it is possible to activate and use
maintenance programs consisting of maintenance groups only having convenience
tasks defined.
Prerequisites
- A maintenance program in the Preliminary status must exist.
- One or more serial parts and belonging revisions must have been assigned
to the maintenance program.
- A maintenance group and maintenance intervals and/or
convenience tasks must exist for the maintenance program.
System Effects
- The maintenance program is activated.
- If a new revision of the maintenance program is set to the Active
status, the previously active maintenance program revision will be set to
the Obsolete status.
- When activating the first maintenance program for a certain part number
and revision, all relevant serials will automatically be set to Out of
Operation and Non Operational.
- An entry is created in the maintenance program journal.
- The active maintenance program can be modified by using the Modify
Active Maintenance Program assistant.
- The due calculation for interval maintenance will run automatically for
the serial to calculate due dates and values.
Window
Define Maintenance Program
Maintenance Programs
Related Window Descriptions
Define Maintenance Program
Define Maintenance
Program/General
Maintenance Programs
Modify Active Maintenance
Program
Procedure
Option 01:
- Open the
Define Maintenance Program
window and query (F3) for the necessary maintenance program.
- You may also, create a maintenance program in this
window (F5). Before the maintenance program can be set to Active status
the following requirements must be fulfilled:
- Serial parts and part revisions must be defined
for the maintenance program.
- Maintenance groups and maintenance plans and/or
convenience tasks must have
been entered for the preliminary maintenance program.
- Right-click anywhere in the header or the
General
tab, point to Status, and click Set Active.
Option 02:
- Open the Maintenance Programs
window populate (F2) or query (F3) for the necessary maintenance program. To create a maintenance program refer step 2
described in option 01.
- Select the row that holds the maintenance program,
right-click and point to Status, then click Set Active.