Create Work Center
Explanation
Use this activity to create and revise a work center. The information entered is used
when working with operations, shop orders, master scheduling, MRP, and cost estimates.
The work center is also a resource
that can be used eg in project planning and maintenance.
Once a work center is created, can use the
Setup Matrix
tab to create a setup matrix. See Activity description for Create
a Setup Matrix.
For outside work centers, a supplier can be entered, but it is not mandatory. If a supplier is
entered for an outside work center,
then this supplier will be used when creating a Purchase Requisitions or Purchase
Orders for outside work centers.
The outside operation report level option is set as a default for outside
operations using the outside work center. Updating the values on an outside work
center will not change setting on previously created operations and routings using the same
work center.
Prerequisites
This activity has the following prerequisites:
- You must have created a site to which you can connect the work center.
- If you want to use a calendar for the work center other than the site
calendar, this calendar must be defined before you create the work center.
- If you want to connect the work center to a production line or
department, this information must be registered before you create the work
center.
System Effects
As a result of this activity:
- The system creates a new work center.
- When you enter an internal work center, cost sets 1, 2, 3, and 4 are
automatically created for it.
- The work center can be linked to a production line.
- The work center can be associated with inbound
and/or outbound inventory locations.
- The work center can be associated with
characteristics.
- The work center is also a resource. The work
center will be connected to the resource structure that
is default for the company associated with the site.
Window
Work Center
Related Window Descriptions
Work Center
Work Center/Locations
Work Center/Characteristics
Procedure
- Open the Work Center window.
- Click New on the toolbar.
- Type the short code of the work center in the Work Center field. This code can consist of up to five alphanumeric characters.
- Type a description of the work center in the Description field.
- In the Site field, specify the site at which the work center is
to be used. Use the List of Values to
select from available sites.
- Specify the work center's Queue Time.
- In the Work Center Code list box, specify whether the work center
is internal or outside.
- Select a calendar for the work center in the Calendar ID field. Use the
List of Values
to select from available calendars. The site calendar appears as the
default.
Type the work center's percentage of use in the Utilization
field. The default value is 100 percent.
This value will affect how big share of the total work time defined in the
calendar that will be considered available for scheduling by CRP and shop
order infinite scheduler.
- Select a Unit of Measure to be used for the work center's
capacity. If the work center's usage code is Active, its unit of measure
must be Hours. If its usage code is Planned or Inactive you can use any unit
of measure.
- In the Sched. Capacity list box, specify whether finite or
infinite schedule capacity is to be used.
This value will only affect operations scheduled by IFS/Advanced Planning
Board, or IFS/Constraint Based Scheduling.
- Select the suitable value from the Outside Reserve/Backflush option
to decide if reserve and/or backflush should be allowed further down in the
reserve/backflush hierachy.
- If you want to link the work center to a production line, type the ID
for the production line in the Production Line field in the
Detail tab window. Use the
List of Values to select from available production lines.
- If you want to link the work center to a cost center, type the cost
center ID in the Cost Center ID field in the
Detail
tab window. Use the List of Values
to select from available cost centers.
- Specify the work center's average capacity in the
Average Capacity field in the
Detail
tab window.
- If you want to link the work center to a department, type the number of
the department in the Department field in the
Detail
tab window. Use the List of Values to
select from available departments.
- Specify the work center's maximum hours per operation and day in the
Max Hours Per Operation field in the
Detail
tab window. This value will restrict how many work hours a single operation
can be scheduled for on the work center per day.
- If the work center code is Outside Work Center, Supplier
field will be enabled. Entering a value in the Supplier field is optional. Use the List of Values to select from
available suppliers.
- In the Auto Report Labor Time with Qty list, specify in which
situations labor time should be reported when a quantity is auto reported on
operations performed on this work center.
- In the Auto Report Machine Time with Qty list, specify in which
situations machine time should be reported when a quantity is auto reported
on operations performed on this work center.
- Save the changes.
- If you want to associate inbound and/or outbound
inventory locations for the work center, list them in the Locations
tab.
- If you want to associate characteristics relevant
for the planning and scheduling on the work center, list them in the Characteristics tab.
- Save the changes.