Use this activity to copy the existing cost, contingency, additional costs and markup build-up for a designated version to the selected version. The existing cost, cost contingency and markup build-up for the selected version is removed and replaced with the copy from version’s. This activity can be performed by right-clicking from the item header in the Items tab.
This activity requires that an estimate header exists with more than one version and there are differences between the versions regarding the cost, contingency and markup build-up. The version to copy to cannot be Cancelled.
As a result of this activity, the cost, contingency and markup build-up for the selected version is applied on another Version ID. The existing cost, contingency and markup build-up for the copy to version is removed.
Note: Item ID and Selected Version are predefined in the Copy from Version dialog and are read only.