Finite Schedule CAMRO Interim Order Structure

Explanation

Use this activity to finite schedule all shop orders connected to the interim order structure using IFS/Constraint-Based Scheduling (CBS). Typically this will be done after disconnecting a repair order from the interim order structure. This activity will not update any date fields on interim orders belonging to the order structure. You will still need to right-click in the header of CAMRO Interim Order Structure window and click Update Dates From Supply to pull the dates from the corresponding supply shop orders into the scheduled start and finish date fields in the interim orders.

Prerequisites

The interim order structure that will use finite scheduling cannot be in a Canceled or Closed state. In addition, at least some of the interim orders in the order structure must be released. The site associated with the overhaul part must be CBS scheduled.

System Effects

As a result of this activity the start and finish dates of the shop orders connected to the interim order structure may be changed. 

Window

CAMRO Interim Order Structure

Related Window Descriptions

CAMRO Interim Order Structure

Procedure

  1. From the Interim Header ID list, select the interim order structure that will use finite scheduling to schedule the corresponding supply shop orders.
  2. Right-click and then click Finite Schedule Order to finite schedule the supply shop orders connected to the interim order structure.