Update Project Material Cost from PQL
Explanation
You can override the project material cost with the supplier price from the
Project Quotation List (PQL).
See also Monitor Project Part
Definition, and Enter
Preliminary Planned Cost in Project Management.
Prerequisites
- The Request For Quotation (RFQ) has
resulted in an approved Supplier Agreement(for part) or an approved Purchase Order (for no-part),
or you must have chosen Get Best Supplier Price from the right mouse button
menu in PQL and resulted in a supplier price.
System Effects
- The project cost for the project item(s) will be updated with the supplier price.
Window
Project Product
Project Item Navigator
Related Window Descriptions
Project Product/Items
Project Item
Navigator/Cost
Project Product/Part
Definition
Procedure
To update the project material cost for all items with
same part revision, follow these steps:
- Select the item in
Project
Product/Part Definition or
Project Part
Definition.
- Select the Get Supplier Price
option from the right mouse button
menu.
- Select the Set Project Cost like Supplier Price for all items
option from the right mouse button menu.
To update the project
material cost for specific item(s), follow these steps:
- Select the item(s) in
Project
Product/Items or in
Project Item
Navigator/Cost.
- Select the Update Project Material Cost from
PQL option from the right
mouse button menu.