Update Project Operation

Explanation

The most current operations in the standard manufacturing structure may not always be reflected in the project delivery structure. Using this activity you are able to update the list of operations given in the Project Item Navigator/Project Operations tab with the latest operations from the manufacturing routing operations or from the template operations. For configurable parts, configuration rules will be re-executed when the Update Operations menu option is selected.

Prerequisites

System Effects

Window

Project Item Navigator/Project Operations

Related Window Descriptions

Project Item Navigator/Operations

Procedure

  1. Open the Project Item Navigator window, query for the required project and select the appropriate item.
  2. Click the Project Operations tab, right-click and select Update Project Operations menu option.
  3. If there are any modified routing or template operations, you will receive a warning message.
  4. Click OK to update the operations.