Change Inventory Part Location in Project Delivery
Explanation
This option will allow a multi site company to move parts
between its sites. The company will have the ability to send or receive any items
required for a Delivery Project from another site that belongs to the
project. This will help the company to meet demands from its delivery projects
with ease and transfer parts to sites when the capacity on one site is high.
Prerequisites
- To be able to move parts to a site other than the default user site, the
site must have been connected to the user ID in the
Sites
per Users form.
- To move the parts in project
inventory to a location at a different site, that site must have been
defined as an allowed site for the project in the
Projects/Site
tab.
System Effects
- The parts will be transferred between the sites as required.
- The On Hand Qty field will be changed according to your change.
Window
Project Product
Project Item
Navigator
Change Inventory Part
Location
Related Window Descriptions
Project Product/Items
Project Item Navigator/Consist
of
Change Inventory Part Location
Procedure
This option is available in the Project Product/Items
tab and Project Item
Navigator/Consist Of tab:
- In any of the above windows query for your project and select the parts
that you wish to transfer.
- Right click and select the Change Inventory Part Location menu
option.
- In the Move Inventory Part window enter a new
line and specify the
quantity you wish to transfer in the Qty to Move field along with the
required site.
- Save the change.
- Observe that the Available quantity and the On hand quantity will change
according to the change you made.